- 20.2.14 Quoted for infinity 2
- 1.3.14 Paid MJH deposit
- 1.4.14 Deposit variation 1
- 17.4.14 Deposit variation 2
- 27.3.14 Pre-walk through My choice studio
- 28.5.14 Deposit variation 3
- 9.5.14 Consolidated tender
- 9.5.14 Land Settled
- 12.5.14 CT sent to design department
- 26.5.14 My Choice Colour appointment
- 28.5.14. Preliminary plans
- 10.6.14 Accepted preliminary Plans
- 24.6.14 Contract Plans
- 1.7.14 Accepted contract plans signed
- 11.7.14 Plans Lodged to council
- 23.7.14 DA +CC plans approved by council
- 23.7.14 Electrical appointment my choice studio
- 27.8.14. On construction List
- 2.9.14 Orders Placed and sent to slab supervisor
- 3.9.14 Site Pegged
- 9.914 Site Cut
- 10.9.14 Sediment Control
- 12.9.14 Drainage
- 23.9.14 Formworks
- 24.9.14 Piering, Termite protection, 3 Phase connection
- 26.9.14 Slab Complete
- 1.10.14 Frame walls commenced
- 9.10.14 Windows sliding doors in
- 13/10/14 Frames completed! Bricks commenced
- 27/10/14 Bricks complete
- 29/10/14 Fascia & Guttering & Bricks cleaned
- 31/10/14 Roof Complete
- 5/11/14 Plumbing & electrical
- 7/11/14 Eaves Complete & carpentry
- 7/11/14 Air conditioning installation
- 7/11/14 Insulation commenced
- 11/11/14 Site cleaned up
- 14/11/14 Gyprock complete
- 25/11/14 Cornices Complete
- 26/11/14 Garage door On Locked Out!
- 27/11/14 Kitchen In and bathroom vanities and commenced
- 27/11/14 Waterproofing commenced
- 2/12/14 Architraves and Internal Doors
- 9/12/14 Tiles commenced
- 15/12/14 Tiles complete
- 15/12/14 Painting commenced
- 24/12/14 Ceaserstone benches on
- 13/1/15 Painting Complete
- 20/1/15 Door handles carpentry complete
- 21/1/15 Apliances in
- 23/1/15 Shower screens in
- 24/1/15 PCI + splashback