Timeline

  • 20.2.14   Quoted for infinity 2
  • 1.3.14     Paid MJH deposit
  • 1.4.14     Deposit variation 1 
  • 17.4.14   Deposit variation 2
  • 27.3.14   Pre-walk through My choice studio
  • 28.5.14   Deposit variation 3
  • 9.5.14     Consolidated tender
  • 9.5.14     Land Settled
  • 12.5.14   CT sent to design department
  • 26.5.14    My Choice Colour appointment
  • 28.5.14.   Preliminary plans
  • 10.6.14    Accepted preliminary Plans
  • 24.6.14    Contract Plans 
  • 1.7.14      Accepted contract plans signed
  • 11.7.14    Plans Lodged to council
  • 23.7.14    DA +CC plans approved by council
  • 23.7.14    Electrical appointment my choice studio
  • 27.8.14.   On construction List
  • 2.9.14      Orders Placed and sent to slab supervisor
  • 3.9.14      Site Pegged
  • 9.914       Site Cut
  • 10.9.14    Sediment Control 
  • 12.9.14    Drainage 
  • 23.9.14    Formworks
  • 24.9.14    Piering, Termite protection, 3 Phase connection
  • 26.9.14    Slab Complete
  • 1.10.14    Frame walls commenced 
  • 9.10.14    Windows sliding doors in
  • 13/10/14  Frames completed! Bricks commenced 
  • 27/10/14  Bricks complete
  • 29/10/14  Fascia & Guttering & Bricks cleaned
  • 31/10/14  Roof Complete
  • 5/11/14    Plumbing & electrical
  • 7/11/14    Eaves Complete  & carpentry
  • 7/11/14    Air conditioning installation 
  • 7/11/14    Insulation commenced
  • 11/11/14  Site cleaned up 
  • 14/11/14  Gyprock complete 
  • 25/11/14  Cornices Complete
  • 26/11/14  Garage door On Locked Out!
  • 27/11/14  Kitchen In and bathroom vanities and commenced
  • 27/11/14  Waterproofing commenced 
  • 2/12/14    Architraves and Internal Doors
  • 9/12/14    Tiles commenced
  • 15/12/14 Tiles complete 
  • 15/12/14  Painting commenced
  • 24/12/14  Ceaserstone benches on
  • 13/1/15    Painting Complete
  • 20/1/15    Door handles carpentry complete  
  • 21/1/15   Apliances in
  • 23/1/15    Shower screens in
  • 24/1/15    PCI + splashback
  •  

No comments: