Architraves and internal Doors 2/12/14
Kitchen Installation,bathroom vanity & waterproofing 27/11/14
Add caption |
Garage Installation 25/11/14
Cornices & finishing Gyprock prep complete 25/11/14
Gyprock Walls Complete 13-14/11/14
Eaves, finishing carpentry, electrical, plumbing, insulation and air cond installation all in 1 week!
3-7/11/14
Roof complete 30-31/10/14
Bricks Complete 27/10/14
Fascia & Guttering and bricks cleaned 28-29/10/14
Bricks continued 18/10/14
Frames complete 15/10/14
Bricks Commenced 13/10/14
First layer of bricks started. Wet weather holding up! |
Bricks delivered 10/10/14
Windows sliding Doors in 9/10/14
Frames continued 5/10/14 |
Door Jambs in
3/10/14
Frames continued
roof trusses up
2/10/14 Frames continued
Frames Commenced 1/10/14
Slab Complete 26/9
Piering, waffle pods, formwork and Termite protection23-24/9 |
Drainage 22/9/14 |
Add caption |
Never been so happy to see this sign :)12/9/14 |
At the end of the drive I found they had put up fencing & spotted a portaloo 12/9/14 |
Block drying out well! thanks to the sunny day yesterday and a bit of wind12/9/14 |
Don't know why but I only have part of fencing.12/9/14 |
Site cut 9/9/14 |
The day after site cut and a heavy rain 10/9/14 |
Sediment control 10/9/14 |
Pegged 3/9/14 |
3/9/14 |
No comments:
Post a Comment